Change of one of the nitrogen tanks in the Cluster building

< Back to notices
 30/04/2024  > 10/05/2024

Change of one of the nitrogen tanks in the Cluster building

On Tuesday 7 May, one of the nitrogen tanks in the Cluster building will be replaced. Scheduling and its effects will be as follows:

  • Tuesday 7 May: replacement of a 3,000-litre nitrogen tank with a 10,000-litre tank. The work requires that access to the forecourt of the Cluster II building be closed to goods transport vehicles all day long. The nitrogen tank filling service will not be available. Users should plan to fill tanks on Monday 6 May.
  • Wednesday 8 May: cooling and filling of the new tank. The work requires that access to the forecourt of the Cluster II building be closed to goods transport vehicles all morning.